The Periodic Progress Report

Periodic reports are used for longer projects. They are generally written at specific intervals during the project. For example, a periodic project report may be written weekly, biweekly, monthly, or quarterly. They also detail a period of time. They can detail a specific week, bi-weekly period, monthly period, or quarter.

The compartments for a periodic progress report are as follows:


  1. The Planned Work sub-compartment tells what should have been accomplished during the period of time the report covers. It's usually combined with the Work Done compartment, or it can be omitted completely.

  2. The Work Done sub-compartment tells what was actually done during the reporting period. To make writing this sub-compartment easier, open up with a summary of what has been done, use sub-paragraphs to detail what has been done, refer to any attachments, and then explain any deviations from the plan or schedule, as well as anything that affected progress.

  3. The Problems sub-compartment tells about anything that's caused the plans or schedule to change. In addition, it should detail any actions taken to overcome any problems, if the actions were successful, if the problems still exist, and what actions will be taken to avoid future problems or make up for time lost on the project.

  4. The Schedule sub-compartment tells if the project was on schedule, ahead of schedule, or behind schedule during the reporting period. Use hours, days, or weeks to state the time. It also tells when the project will be back on schedule, if behind. In addition, it gives a revised schedule for the next reporting period when necessary.



]]>